IMPLEMENTATION TIMELINE SCHEDULE

 

Timeline

Necessary Steps

CleanRiver Implementation

1 week

Site assessment and pre-audit

Audit report, proposal and cost estimates

1 month

Senior Management commitment

Presentation and draft communications from Senior Management

1 month

Establish Implementation Team

Action plan and communications plan

6 weeks

Establish equipment types, quantities, and distribution plan, order equipment

Equipment list, description, quantities, and distribution plan

6 weeks

Set up Recycling Team who represent their areas

Outline of roles and responsibilities for Recycling Team members

8 weeks

Conduct training sessions for the Recycling Team

Communications package and timelines for Recycling Team

8 weeks

Review waste, recycling, and janitorial contracts

Recommended clauses to improve contracts

10 weeks

Train janitorial staff, recycler, and building manager

Communications materials

12 weeks

Plan and launch program

Official launch of program

4 months

Post launch audit

Preliminary results report

6 months

Monitor and provide feedback

Monitoring and feedback plan and final evaluation and results report

9 months

to 1 year

Review how program can be rolled out to other facilities

CleanRiver Implementation Plan

 

BENEFITS

  • Proven diversion record of 80% and higher of office garbage
  • Increased savings by eliminating the janitors going desk to desk
  • Increased revenues generated from recycled materials (minimum 50%)
  • Reduction in tipping and hauling fees
  • Getting people involved makes recycling a more personal issue
  • Color-coded products for ease of identification
  • All plastic products manufactured with post consumer recycled content
© 2011. All Rights Reserved to Midpoint International Inc                                                       Powered by pavliks.com